Faidley Avenue Extension from North Road to Irongate Avenue

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

Project Description

This project extended paving to join the two existing segments of Faidley Avenue; between North Road and Irongate Avenue. 

 

The Diamond Engineering Co. of Grand Island, Nebraska was awarded the $925,292.70 contract on September 23, 2014, with completion of the project July 2016 for a total construction cost of $958,552.06, which was an under-run of $15,769.21. 

 