Capital Avenue Drainage Improvements;

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

This project built a portion of drainage associated with the Capital Avenue- Moores Creek Drainway to North Road Roadway Improvements; Project No. 2020-P-1.  It also allows for better drainage from the North Road improvement project and future paving & drainage improvements west of North Road.  

On November 24, 2020, via Resolution No. 2020-313, Grand Island City Council awarded construction of Capital Avenue Drainage Improvements- North Road to Moores Creek; Project No. 2020-D-2 to Van Kirk Sand and Gravel, Inc. d/b/a Van Kirk Bros. Contracting of Sutton, Nebraska in the amount of $215,348.70.

On May 25, 2021, via Resolution No. 2021-120, Grand Island City Council approved Change Order No. 1 at no additional cost to extend the completion date of the project from May 15, 2021 to June 14, 2021.

On September 28, 2021, via Resolution No. 2021-256, Grand Island City Council approved the Certificate of Final Completion for this project in the total amount of $314,952.79, which includes Public Works engineering services, easement acquisitions and subsequent filing fees, storm sewer televising, and bid solicitation advertising.