This project will plan, design and build two (2) small projects as part of the larger Moores Creek Drainage Extension project. The extension of Moores Creek Drainage system was investigated in a 2017 engineering study that was completed by JEO for the City of Grand Island. This study was based on a past Central Platte Natural Resources District (CPNRD) drainage plan for Grand Island and focused on hydrologic sizing and operation of Moores Creek drainage ditch to serve current areas of southwest Grand Island, as well as the proposed US Highway 30 realignment project. A partial design was completed and the City coordinated with the Nebraska Department of Transportation (NDOT) to incorporate provisions for the drain extension in the US Highway 30 Realignment project.
The two (2) small projects to be designed and constructed consist of the culvert extension of the ditch under Engleman Road near the Grand Island Utilities water storage tower (2021-D-2(A)), and the detention cell on the southwest corner of Old Potash Highway and North Road (2021-D-2(B)).
On October 12, 2021, via Resolution No. 2021-275, City Council approved an agreement with Olsson, Inc. of Grand Island, Nebraska in the amount of $72,600.00 for professional engineering consulting services.
On March 22, 2022, via Resolution No. 2022-72, City Council approved Amendment No. 1 to the original agreement with Olsson, Inc., in the amount of $50,700.00, to include construction phase services.
On January 25, 2022, via Resolution No. 2022-26, City Council approved the construction award of The Diamond Engineering Company of Grand Island, Nebraska for Moores Creek Drainage Culvert Extension; Project No. 2021-D-2(A) in the amount of $267,262.20.
On July 26, 2022, via Resolution No. 2022-191, City Council approved Change Order No. 1 with The Diamond Engineering Company, in the amount of $67,907.19, to address debris and a fiber duct lowering that were discovered during construction.
On April 26, 2022, via Resolution No. 2022-118, City Council approved the construction award to Mid Nebraska Land Developers, LLC of Aurora, Nebraska for Moores Creek Storm Sewer Improvements; Project No. 2021-D-2(B) in the amount of $146,420.35.
On July 26, 2022, via Resolution No. 2022-185, City Council approved Change Order No. 1 with Mid Nebraska Land Developers, LLC, at no additional cost, to allow for a time extension from June 1, 2022 to September 30, 2022 due to workload.
On September 27, 2022, via Resolution No. 2022-268, City Council approved Change Order No. 2 with Mid Nebraska Land Developers, LLC, in the amount of $7,094.15, to allow for additional culvert work based on drainage modifications made to the adjacent subdivision.
On April 9, 2024, via Resolution No. 2024-97, City Council approved the Certificate of Final Completion for Moores Creek Drainage Culvert Extension; Project No. 2021-D-2(1) and Moores Creek Storm Sewer Improvements; Project No. 2021-D-2(B), in the total amount of $625,338.52.