Wastewater Treatment Plant Flow Improvements; Project No. 2020-WWTP-4

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Public Works Engineering staff identified several areas in which improvements are desired to be evaluated.  Staff is looking at the following items to improve plant operations and monitoring.

  • Industrial Flow Measurement
  • Industrial Flow Diversion
  • Buried Infrastructure Evaluation
  • Internal Recycle System

On December 22, 2020, via Resolution No. 2020-340, City Council approved an agreement with HDR Engineering, Inc. of Omaha, Nebraska in the amount of $437,955.00 for engineering consulting services.

On January 25, 2022, via Resolution No. 2022-24, City Council approved Amendment No. 1 with HDR Engineering, Inc., in the amount of $644,177.00 to allow for additional design, construction phase and project closeout services. 

On March 22, 2022, via Resolution No. 2022-71, City Council approved the construction contract with Building Crafts, Inc. of Red Oak, Iowa, in the amount of $8,356.00.00.

On March 26, 2024, via Resolution No. 2024-85, City Council approved Change Order No. 1 with Building Crafts, Inc. in the amount of $263,267.29 for a revised contract price of $8,619,267.29.