Asphalt Maintenance; Project No. 2020-AC-1

The asphalt resurfacing project includes a mill and overlay of the existing asphalt roadways.  This type of construction is a mobile operation and includes short duration driveway closures.  On all roadway segments, traffic will be maintained on one lane of traffic with flaggers through the construction zone.  Please observe the temporary traffic control signs and flaggers.  Before the lay down operation begins, the contractor will spray a layer of fresh oil.  Please do not drive through the fresh oil. 

The following locations are included in this project.

  • Husker Highway; US Highway 30 to Regal Drive

  • Engleman Road; Husker Highway to US Highway 30

  • Schimmer Road; North Road to Blaine Street

  • Blaine Street; Schimmer Road to US Highway 34

On March 24, 2020, via Resolution No. 2020-76, Grand Island City Council awarded Gary Smith Construction Co., Inc. of Grand Island, Nebraska the bid in the amount of $898,534.85 for Asphalt Resurfacing Project No. 2020-AC-1.

On September 22, 2020, via Resolution No. 2020-231, Grand Island City Council approved Change Order No. 1 which allowed for a time extension from September 4, 2020 to November 15, 2020 to complete this project. 

On November 24, 2022, via Resolution No. 2020-304, Grand Island City Council approved Change Order No. 2 which allowed for a time extension from November 15, 2020 to July 1, 2021 to complete this project.

On July 13, 2021, via Resolution No. 2021-165, Grand Island City Council approved Change Order No. 3 which allowed for a time extension from July 1, 2021 to August 15, 2021 to complete this project.

On September 14, 2021, via Resolution No. 2021-227, Grand Island City Council approved the Certificate of Final Completion for Asphalt Resurfacing; Project No. 2020-AC-1 in the total amount of $911,473.58, which includes Public Works engineering services, identifying section corners, quality assurance, and bid solicitation advertising.