Asphalt MAsphalt Maintenance; Project No. 2019-AC-1
The City of Grand Island will be resurfacing the following asphalt roadways this year:
4th Street: BNSF Railroad to Beal Street
4th Streeet: Congdon Avenue to 7th Street
Sky Park Road: 7th Street to White Cloud Road
Airport Road: Homestead Drive to Sky Park Road
The asphalt resurfacing project includes a mill and overlay of the existing asphalt roadways. This type of construction is a mobile operation and includes short duration driveway closures. On all roadway segments, traffic will be maintained on one lane of traffic with flaggers through the construction zone. Please observe the temporary traffic control signs and flaggers. Before the lay down operation begins, the contractor will spray a layer of fresh oil. Please do not drive through the fresh oil.
On February 26, 2019 City Council awarded a construction agreement to Gary Smith Construction Co., Inc. of Grand Island, Nebraska in the amount of $607,377.25.
On August 27, 2019, via Resolution No. 2019-260 , City Council approved Change Order No. 1 to allow for sprinkler repair at the Central Nebraska Regional Airport, due to damage during roadway resurfacing in this area. Change Order No.1 covers the materials, labor and equipment to make such sprinkler repairs. The extra work adds a total cost of $2,560.80 to the project, resulting in a revised contract amount of $609,938.05.
On December 17, 2019, via Resolution No. 2019-368, Grand Island City Council approved the Certificate of Final Completion for Annual Asphalt Resurfacing; Project No. 2019-AC-1 in the total amount of $614,364.38.