Curb Ramp Project No. 2019-CR-2-CDBG
Construction for continued curb ramp improvements is scheduled for Summer 2019. This project is partially funded by a Community Development Block Grant (CDBG) in the amount of $145,500.00.
Curb ramps will be constructed at the following intersections:
7th Street
Superior Street
Market Street
Vine Street
Meves Avenue
Memorial Drive
Ashton Avenue
Oak Street & Bike Trail
Ashton Avenue
Plum Street
Memorial Drive
Maple Street
Cherry Street
Memorial Drive
Joehnck Road
Cherry Street
Meves Avenue & Plum Road
Joehnck Road
Meves Avenue
MacArthur Avenue
Cherry Street
Meves Avenue
MacArthur Avenue
Martin Avenue
The City of Grand Island has an on-going curb ramp program to upgrade public sidewalk ramps to conform to American with Disabilities Act (ADA).
On April 9, 2019 City Council awarded the construction agreement to Galvan Construction, Inc. of Grand Island, Nebraska in the amount of $152,212.00.
On September 10, 2019 City Council approved a Certificate of Final Completion for Curb Ramp Project No. 2019-CR-2 CDBG with Galvan Construction, Inc. in the amount of $141,451.72, and additional project expenses of $14,006.25; resulting in a total project cost of $155,457.97.