Remove trees and upgrade ditch to allow for proper maintenance and improved channel flow.  Plan development is currently underway.

On February 26, 2019, via Resolution No. 2019-80, City Council awarded a construction agreement to Starostka Group Unlimited, Inc. of Grand Island, Nebraska in the amount of $247,981.06.

On August 27, 2019, via Resolution No. 2019-256, City Council approved Change Order No. 1 granting a time extension from September 1, 2019 to May 31, 2020 for the project completion date due to the continual rainfall this spring/ summer that saturated the ground, making the work area inaccessible.  There was no modification to the contract amount with this change order.

On March 24, 2020, via Resolution No. 2020-81, City Council approved Change Order No. 2 in the amount of $15,000.00 due to the continual rainfall experienced in 2019 and the need to rebuild the temporary storm water diversion to facilitate this project.  Such change order resulted in a revised contract amount of $262,981.06.

May 26, 2020, via Resolution No. 2020-124, City Council approved Change Order No. 3 in the amount of $7,868.00 to allow repair of damaged asphalt in the Eagle Scout Lake parking area and a sanitary sewer force main in the Vet's Sports Complex.  This change order resulted in a revised contract amount of $270,849.06.

On February 9, 2021, via Resolution No. 2021-21, Grand Island City Council approved the Certificate of Final Completion for North Broadwell Avenue Drainage; Project No. 2018-D-1 in the total amount of $298,799.62, which includes Public Works engineering service and fiber relocation.