Tri Street Drainage Improvements; Project No. 2023-D-1
The Public Works Engineering office has received multiple complaints from residents in the neighborhood of Tri Street and US Highway 34 regarding poor drainage after the recent development in the area. It is recommended to amend the engineering services agreement with JEO Consulting Group, Inc. to evaluate and possibly design a solution. A preliminary design of Tri Street south to the end of existing pavement on Lake Street would be done to make sure a future paving project/district would not be hindered by any possible work done today.
On May 24, 2022, via Resolution No. 2022-144, City Council approved Amendment No. 2 in the amount of $13,895.00 with JEO Consulting Group, Inc. of Grand Island, Nebraska for the Various Drainage Projects FY22 to include Tri Street Drainage Improvements.
On May 23, 20203, via Resolution No. 2023-131, City Council approved Amendment No. 3 to the original agreement with JEO Consulting Group, Inc. in the amount of $55,785.00, resulting in a revised amount of $179,695.00.
On May 7, 2024, via Resolution No. 2024-114, City Council approved Amendment No. 4 to the original agreement with JEO Consulting Group, Inc. in the amount of $82,140.00. Such amendment allowed for construction observation and resident communication of improvements and resulted in a revised agreement amount of $261,835.00.
On March 25, 2024, via Resolution No. 2024-82, City Council approved the bid award to The Diamond Engineering Company of Grand Island, Nebraska in the amount of $464,833.70 for the construction of Tri Street Drainage Improvements; Project No. 2023-D-1.
On August 13, 2024, via Resolution No. 2024-173, City Council approved Change Order No. 1 to the original contract with The Diamond Engineering Company at no additional cost. Change Order No. 1 provided a time extension to complete the project from September 6, 2024 to December 15, 2024 due to wet weather conditions delaying the project.
On January 14, 2025, via Resolution No. 2025-11, City Council approved Change Order No. 2, in the amount of $28,202.00, to the original contract with The Diamond Engineering Company to allow for quantity rectification and an unplanned sanitary sewer relocation, Such change order resulted in a revised contract amount of $493,035.70.
On March 11, 2024, via Resolution No. 2025-78, City Council approved the Certificate of Completion for such project in the total amount of $679,648.46.